Operations Updates

Elevators

Full upgrade

November 15 Start Date

Beginning November 15, construction will begin with removing the surrounding glass on both HR and LR elevators.

This work will take place AFTER HOURS (6pm to 6am) with continual construction throughout the coming weeks.

Thank you for your patience!

Lobby

Full lobby renovation

Upcoming Phases of Construction

November 13-19:  The glass around the HR and LR elevators will be removed.

November 19-21:  The removal of travertine on the dividing walls and elevators will begin.

November 22-December 1:  Demolition of dividing wall.

December 1-December 31:  Replacement of exterior windows and glazing.

+15 Patio

Tenant Outdoor Lounge Area

Expected Completion:

In June, Tillyard began Phase One of our patio upgrade. Fresh paint, new patio furniture, a green wall, and our fabulous city mural were just the start of many improvements.

Beehives

BUZZ BUZZ BUZZ

The hives have been winterized, the honey has been harvested, and Tillyard will be distributing the honey to the tenants this week.

Switchgear Maintenance

SUNDAY, OCTOBER 3, 7am-2pm

TENANTS WILL HAVE NO ACCESS TO THE BUILDING

Completed.

Fire Alarm Testing

SEPTEMBER 27 - 30

Testing will take place from 6pm to 6am.

Completed.

Conference Room

Men's and Women's rest rooms are under construction.

Expected Completion:

Completed.

30th Floor

New Show Suite

Expected Completion:

Completed. Thank you for your patience.

Roof Replacement

Please be aware of how this might impact you!

Expected Completion:

We are thrilled to announce that this project has been completed.

Thanks to our partners at RJC and Flynn Roofing.